Latest Repair Work Progress ReportThe following was originally published in the January 2003 edition of the Parish Magazine
We are now three months into the roof repairs and the project is turning out
to be fraught with difficulties, as I suppose all work of this kind is. Some of
the difficulties are associated with the repairs themselves, and some with the
financial side.
The work itself is actually progressing well, with at least three roof slopes
refurbished and re-tiled. These are the Nave north side, the Chancel north side
and the east side of the south transept. And very good they look too. Also the
gutters and down-pipes have all been renewed or refurbished.
Our troubles started when the contractors started taking the roofs off. First,
there were more areas of woodwork that needed replacing than we had originally
been led to expect. Then it was discovered that the plaster ceilings of the nave
and chancel are largely holding themselves up, with rather little help from the
lathes and from the woodwork that is supposed to be supporting them. With the
large amount of overhead activity that has been going on, we have been given
dire warnings about falling plaster. We have therefore had to restrict use of the
church to the south aisle, the transepts and the crossing. By the time you read
this, the nave and chancel will probably be full of scaffolding so that use would
be impossible anyway. We very much hope that this will be gone by the time we have
a new member of the team installed.
English Heritage has increased its grant enough to encourage us to go ahead
with this work, but there are some "buts". First, there is not nearly enough for
the "proper" repair of the ceilings, so we are going to get a temporary safety
net until a lot more money can be raised.
The second "but" is that the improved English Heritage grant is for 66% of
£98,000, up from 80% of £47,000. When we add in the other charities that have
already agreed to contribute, this means that we now in debt to the tune of
£10,000. When you receive our begging letter, please do what you can to help.
The alternative was for the contractors to stop work with the roofs unfinished
and the nave and chancel out of use for the foreseeable future.
RICHARD STAYNER
Secretary to Stanton Lacy PCC
Addendum - February 1, 2003
The above was written before the drains were checked. The main pipe taking
the roof water away from the foundations is completely silted up for almost
all of its length and will have to be replaced with new. This is actually
within the original budget for once, but the church path is temporarily hazardous.
|